UPGRADE OF FIRE PROTECTION NETWORKS AT 3 SITES
UPGRADE OF FIRE PROTECTION NETWORKS AT 3 SITES (MBAO, PB AND PN) 2023 –2024 The mission concerns the three SENSTOCK sites below: The SENSTOCK MBAO FIRE PROTECTION system includes 2 FIRE PROTECTION tan...
Dec 3, 2024
STUDY AND MONITORING OF THE NEW TANKER LINE
STUDY AND MONITORING OF THE NEW TANKER LINE 2023 This mission consists of carrying out all the technical studies required for the implementation of this new unloading line, with the essential aim of t...
Dec 3, 2024
UPGRADING OF PROCESS LINES
UPGRADING OF PROCESS LINES 2023 Following a gap analysis of the gas and flame detection system at the Mbao Gas Filling Center by comparing existing GF detection installations with current standards, t...
Dec 3, 2024
DESIGN OF A SERVICE PLATFORM FOR SUCTION STRAINER MAINTENANCE
DESIGN OF A SERVICE PLATFORM FOR SUCTION STRAINER MAINTENANCE 2023- 2024 This project involves the design of a service platform to enable VIVO ENERGY to carry out maintenance operations on fire circui...
Dec 3, 2024
3D MODEL OF AN INCINERATION PLATFORM
3D MODEL OF AN INCINERATION PLATFORM 2023- 2024 This project consists in building a 3D model of the incineration platform for SOCOCIM. WISE- LAB's mission is to : Modeling of the structure and ancilla...
Dec 3, 2024
WELDING AND ASSEMBLY PLATFORM
WELDING AND ASSEMBLY PLATFORM 2023 Construction of a welding and assembly platform for a pipeline network; Construction of supports and pulling lines. Client: Touba Oil...
Dec 3, 2024
ELECTRICAL POWER STATION CONSTRUCTION PROJECT
ELECTRICAL POWER STATION CONSTRUCTION PROJECT 2022-2023 Design and sizing of a transformer substation for SOCOCIM. In this project, WISE-LAB's mission is to : Dimensioning the slabs on which the trans...
Dec 3, 2024
CORRECTION PAVING WAREHOUSE FLOOR
CORRECTION PAVING WAREHOUSE FLOOR 2022 Following the renovation of a hangar, Oleosen reinforced the existing footings because the building had to be raised. At the end of the works, during the operati...
Dec 3, 2024
KAEL SOLAR POWER PLANT
KAEL SOLAR POWER PLANT 2020 Construction of a 45MWp Solar Power Plant. Services provided : On-site inspection visits; Drafting of progress reports; Photo reports. Client: ENGIE SENEGAL...
Dec 3, 2024
KAHONE SOLAR POWER PLANT
KAHONE SOLAR POWER PLANT 2020 Construction of a 45MWp Solar Power Plant. Services provided : On-site inspection visits; Drafting of progress reports; Photo reports. Client: ENGIE SENEGAL...
Dec 3, 2024
DIMENSIONAL INSPECTION OF STRUCTURES
DIMENSIONAL INSPECTION OF STRUCTURES 2022 Evaluation of deviations between manufacturing drawings and final structures via 3D scanning. Client: Orsen...
Dec 3, 2024
RE-ENGINNERING BY SCAN 3, MANUFACTURING DRAWINGS AND STP FILES OF PARTS FOR THE MINING SECTOR
RE-ENGINNERING BY SCAN 3, MANUFACTURING DRAWINGS AND STP FILES OF PARTS FOR THE MINING SECTOR 2021-2022 Parts .STP file; Manufacturing drawing. Client: Tanor Granulat...
Dec 3, 2024
  • Prev
  • 1
  • 2
  • 3
  • Next

Follow us


Connect with us
  • 1 Corniche des Mamelles, Dakar Senegal
  • info@energia.sn
  • +221 33 825 22 01
Copyright © WiseGroup

We use cookies to provide you a better user experience on this website. Cookie Policy

Only essentials I agree